No holidays at the construction site!

This month, new plants appeared at the construction site of the „Alarm Clock" Clinic for adults, at the Mazowiecki Bródnowski Hospital.
Today we witnessed bark being sprinkled on new roots. Now we are waiting for the rain.
And inside the clinic building, intensive finishing works are underway and there is already an elevator!

English

"Alarm Clock" Clinic for adults

On the construction site, everyone is working hard! Finishing works inside the building are currently underway.
Formal steps have also been taken to launch the entity that will be the operator of the rehabilitation facility „Alarm Clock Clinic for adults" - Budzik dla dorosłych Sp. Z o.o.

 
English

From above - "Alarm Clock" Clinic for adults

It's summer already.
On this occasion, we flew over the Budzik for adults in Warsaw.
Paths leading to the building have already been created, and railings by the stairs have been installed inside.
Sunshine hearts beat right away

Pictures: Adam Andres

English

Visit at the construction site

The time has come to make decisions about interior colors in the emerging „Alarm Clock" Clinic for adults, at the Mazowiecki Bródnowski Hospital, in Warsaw.

Mrs Ewa Błaszczyk personally came to the construction site, where she saw the progress of the works and selected the colors of the Clinic's interior.

English

Work progress

Meanwhile, new finishing materials are arriving at the construction site of the "Alarm Clock" clinic for adults in Warsaw.
Granite slabs have already appeared on the roof, which will soon be laid. Installation work is still underway inside.
Tiles are already being laid in bathrooms and on the stairs.

English

Construction

Meanwhile, advanced works related to external infrastructure (sidewalks, roads, parking lots) are underway on the premises of the emerging "Alarm Clock" Clinic for adults in Warsaw.
Earthworks are also carried out after the rainwater tanks have been dug in.
In addition, a fully automated heat substation has already been assembled, ventilation systems are being completed and preparations are underway for embedding internal barriers in the building's atrium.
Works related to: wall priming, screeds for cladding and electrical installations are also continued.
English

Spring works

Finishing works are progressing inside the building of the „Alarm Clock" Clinic for adults at the Mazowiecki Bródnowski Hospital.
Currently, chilled water and medical gas installations are being made. Plastering works are also underway on the walls, under plaster and sanding screeds under floor coverings.
We are not afraid of snow ;-)

English

Progress of earthworks

Meanwhile, at the construction site of the "Alarm Clock" Clinic for adults, at the Mazowiecki Bródnowski Hospital, trimming of the parking area was carried out.
At the same time, works related to further trimming and insertion of road resistors around the building are in progress.
Happens!
English

Construction site

Last week, we selected interior finishing materials for the “Alarm Clock” Clinic for adults, under construction, in Warsaw.
"(...) It should be warm and bright (...)" ;-)
By the way, we encourage you to donate 1% of your tax to our Foundation, the Ewa Błaszczyk's "Akogo?" Foundation.
We help people with severe brain injuries who are in a coma, as part of the „BUDZIMY DO ŻYCIA" social campaign!
You can use the free PIT settlement program.
https://pity-format.pl/2021/215_a/page
English

Thank you!

The Ewa Błaszczyk's „Akogo?" Foundation would like to thank the Chancellery of the Prime Minister for the funds granted in 2021.
The Foundation received a subsidy for the emerging "Alarm Clock” Clinic for adults, as part of the submitted offer, under the Act on Public Benefit and Volunteer Work.
The support in the amount of 2,936,044.00 allowed us to finish the construction of the Center at the stage - shell closed. Now we can look at the future differently…